Question: |
My job cost estimates and original budgets amounts don’t align? Why is that? |
Answer: |
This is likely due to having inactivated a cost code in your Company Set Up that had estimated values entered to it. As a best practice, it is recommended that whenever you are inactivating a cost code from the database, to make sure it is not in use on an active project or to zero out any values before inactivating. |