Overview
eSUB’s latest feature enhancement allows users to enable RFI’s to synchronize between eSUB and PlanGrid. The following actions will trigger RFI Synchronization between the associated eSUB and PlanGrid projects:
- The Enable RFI Synchronization setting is enabled in eSUB
- User creates a new RFI
- User edits an existing RFI
- User views the RFI Log
NOTE: RFI’s created prior to enabling RFI Synchronization must be re-saved before appearing in the associated eSUB or PlanGrid project. |
eSUB to PlanGrid RFI Fields
eSUB Field |
PlanGrid Field |
Subject Clarification Requested Answer Return By Date RFI Date Attachments |
Title Question Answer Due Date Sent Date References |
eSUB to PlanGrid RFI Status Fields
eSUB Status |
PlanGrid Status |
Pending Pending Answered Void Pending |
Draft (Green) Open (Blue) Closed (Yellow) Void (Red) Custom (Orange/Violet) |
Table of Contents |
Click Here to view the associated Help Center article.
Associate eSUB Project to PlanGrid Project
Click Here to view the associated Help Center article.
Enable PlanGrid RFI Synchronization
- Go to Start > Settings > Administration > Company Setup
- Select Company Preferences > PlanGrid
- Select the Enable RFI Synchronization check-box
- Select Save Data
Comments