eSUB Academy

Follow

Enter or Edit As Planned / Actual Dates

Enter and edit the as planned / actual hours for an existing Labor Activity on the current Project.

Labor Activity - Displays the Labor Activity description.

As Planned Start Date - Enter/Edit the as planned start date of the Labor Activity.

As Planned Finish Date - Enter/Edit the as planned finish date of the Labor Activity.

Actual Start Date - Enter/Edit the actual start date of the Labor Activity.  This date is automatically populated whenever a Labor Activity is utilized.

Actual Finish Date - Enter/Edit the actual finish date of the Labor Activity.

Click the Save Data button to accept the edited data and file the As Planned / Actual Dates  in your eSUB database.