As Planned Hours

View the As Planned Hour logs (by Labor Activity and by Week) associated with the current Project.

Quick Links

As Planned Hours By Labor Activity - Click this link to view the As Planned Hours By Labor Activity graph.

As Planned Hours By Week - Click this link to view the As Planned Hours By Week graph.

 

Glossary:

As Planned Hours By Labor Activities Log 

Code - Displays the labor activity code.

Labor Activity - Displays the labor activity description.

As Planned Start Date - Displays the as planned starting work date for the associated labor activity.

As Planned End Date - Displays the as planned ending work date for the associated labor activity.

Actual Start Date - Displays the actual starting work date for the associated labor activity.

Actual End Date - Displays the actual ending work date for the associated labor activity.

As Planned Hours - Displays the as planned hours for the associated labor activity.

Actual Hours - Displays the actual hours expended for the associated labor activity.

 

As Planned Hours By Week Log

Week - Displays the As Planned project week number.

Week Start Date - Displays the start date of the associated As Planned week.

Week End Date - Displays the end date of the associated As Planned week.

As Planned Hours - Displays the as planned hours for the associated As Planned week.

Actual Hours - Displays the actual hours expended for the associated As Planned week.