How does the Percent of Efficiency report calculate efficiency?

Question:
How does the Percent of Efficiency report calculate my efficiency?
Answer:

The report calculates your project’s efficiency based upon the following formulas:

Example 1: Right-click and select View Image to view the example

[Used Hours/Total Budgeted Hours] x 100% = Percent Used Hours

then

[Percent Complete/Percent Used Hours] x 100 = Percent of Efficiency

then

[Total Budgeted Hours/[Percent of Efficiency/100] = Projected Used Hours

then

Projected Used Hours – Used Hours = Projected Remaining Hours

 